Plan A : Down Payment Plan (with 10% Rebate)

At the time of Booking 10%
Within 45 days of Booking 75% + EDC + IDC + PLC
At the time of offer of Possession 5%

Plan B : Construction Linked Payment Plan

At the time of booking 10%
Within 45 days of booking 10%
On commencement of construction 10% + 50% of  EDC & IDC
On start of Ground Floor Roof Slab 10% + 50% of  EDC & IDC
On start of First Floor Roof Slab 10%+PLC
On start of Second Floor Roof Slab 10%
On completion of Super Structure 10%
On start of Internal Plaster 9%
On start of Flooring 8%
On start of External Plaster 8%
At the time of offer of possession 5%

Note: PLC - Preferential Location Charges